计及检修过程随机性影响的断路器检修决策方法
熊小伏1, 刘 松1, 张南辉2, 王 建1, 袁 峻2
1.重庆大学 输配电装备及系统安全与新技术国家重点实验室,重庆 400044;2.云南电网有限责任公司昆明供电局,云南 昆明 650011
摘要:
断路器单次检修过程受各方面因素影响,具有一定随机性,尚无较准确的方法描述这一随机性。通过分析单次检修随机性与剩余无故障工作时间之间的关系,建立计及检修过程随机性影响的断路器平均剩余无故障工作时间模型,用以反映检修后断路器可靠性水平。计算断路器单次检修后平均剩余无故障工作时间作为下一个检修优化区间,以检修优化区间内预防性检修费用、故障检修费用和停电损失之和最小为目标函数,制定综合考虑可靠性与经济性的检修策略。通过分析断路器检修退出后剩余系统风险与断路器继续运行对系统潜在风险的贡献度,提出断路器检修紧迫度概念来确定多台断路器在同一时间段检修的检修顺序。最后,以IEEE-RBTS进行算例分析,验证了所提方法的可行性和有效性。
关键词:  断路器  可靠性  预防性检修  故障检修  停电损失  检修顺序  风险分析  检修
DOI:
分类号:
基金项目:
Circuit breaker maintenance strategy considering influence of maintenance process randomness
XIONG Xiaofu1, LIU Song1, ZHANG Nanhui2, WANG Jian1, YUAN Jun2
1.State Key Laboratory of Power Transmission Equipment & System Security and New Technology,Chongqing University,Chongqing 400044,China;2.Kunming Power Supply Bureau,Yunnan Power Grid Limited Liability Company,Kunming 650011,China
Abstract:
Affected by various factors,a maintenance process of circuit breaker has certain randomness,which cannot be accurately described. The relationship between the single maintenance randomness and the remained faultless time is analyzed and an MTTF(Mean Time To Failure) model considering the influence of maintenance process randomness is established to reflect the reliability of circuit breaker after maintenance. The calculated MTTF of circuit breaker after maintenance is taken as the optimization period for next maintenance and with the minimal sum of preventive maintenance cost,fault maintenance cost and outage cost as its objective function,a maintenance strategy considering both reliability and economy is developed. The system risk induced by the quitting out of circuit breaker for maintenance and the potential system risk by its continuous operating are analyzed and a concept of circuit breaker maintenance urgency is proposed,which is used to determine the maintenance sequence for several circuit breakers to be maintained in same period. A case analysis for IEEE-RBTS verifies the feasibility and effectiveness of the proposed method.
Key words:  electric circuit breakers  reliability  preventive maintenance  failure maintenance  outage cost  maintenance order  risk analysis  maintenance