引用本文:徐铭铭,曹文思,姚森,徐恒博,牛荣泽,周宁.基于模糊层次分析法的配电网重复多发性停电风险评估[J].电力自动化设备,2018,(10):
XU Mingming,CAO Wensi,YAO Sen,XU Hengbo,NIU Rongze,ZHOU Ning.Risk assessment of repeated multiple blackouts for distribution network based on fuzzy AHP[J].Electric Power Automation Equipment,2018,(10):
【打印本页】   【HTML】   【下载PDF全文】   查看/发表评论  【EndNote】   【RefMan】   【BibTex】
←前一篇|后一篇→ 过刊浏览    高级检索
本文已被:浏览 4010次   下载 1835  
基于模糊层次分析法的配电网重复多发性停电风险评估
徐铭铭1, 曹文思2, 姚森3, 徐恒博1, 牛荣泽1, 周宁1
1.国网河南省电力公司电力科学研究院,河南郑州450002;2.华北水利水电大学电力学院,河南郑州450045;3.重庆大学电气工程学院,重庆400044
摘要:
介绍重复多发性停电的概念。对95598停电投诉记录、配电网抢修管理平台、配电网运行监测平台等信息系统中的停电数据进行汇总分析,并进行实际调研工作。归纳配电网重复多发性停电常见原因,针对各种原因分别给出影响因数指标,用以衡量配电网重复停电概率水平。应用模糊层次分析法建立指标评价体系,分别从装备水平、运行维护水平和网架结构水平3个方面对配电网重复多发性停电发生概率的影响情况进行评价。针对某实际停电实例进行重复多发性停电风险评估,获得了重复多发性停电综合概率值。
关键词:  配电网  重复多发性停电  模糊层次分析法  综合判断矩阵  停电预警  风险评估
DOI:10.16081/j.issn.1006-6047.2018.10.004
分类号:TM73
基金项目:国家电网公司总部科技项目(SGHADK00PJJS1600050)
Risk assessment of repeated multiple blackouts for distribution network based on fuzzy AHP
XU Mingming1, CAO Wensi2, YAO Sen3, XU Hengbo1, NIU Rongze1, ZHOU Ning1
1.State Grid Henan Electric Power Research Institute, Zhengzhou 450002, China;2.School of Electric Power, North China University of Water Resources and Electric Power, Zhengzhou 450045, China;3.School of Electrical Engineering, Chongqing University, Chongqing 400044, China
Abstract:
The concept of repeated multiple blackouts is introduced. The power outage data of information systems of 95598 power outage complaint recording, distribution network repair and management platform, and distribution network operation and monitoring platform are summarized and analyzed, and the actual investigation work is carried out. The common reasons of repeated multiple blackouts of distribution network are summarized, and the influence factor indexes are given for each reason to measure the probability of the repeated multiple blackouts. The index evaluation system is established by fuzzy AHP(Analytic Hierarchy Process)to evaluate the probability of the repeated multiple blackouts from three aspects, i. e. equipped level, operation and maintenance level, and grid structure level. The risk assessment of repeated multiple blackouts is carried out for an actual power outage case, and the comprehensive probability is obtained.
Key words:  distribution network  repeated multiple blackouts  fuzzy AHP  comprehensive judgment matrix  blackout early warning  risk assessment