引用本文:何成明,王洪涛,王春义,韦仲康.风电功率爬坡事件作用下考虑时序特性的系统风险评估[J].电力自动化设备,2016,36(1):
HE Chengming,WANG Hongtao,WANG Chunyi,WEI Zhongkang.Risk assessment considering time-sequence characteristics for power system with wind power ramp event[J].Electric Power Automation Equipment,2016,36(1):
【打印本页】   【HTML】   【下载PDF全文】   查看/发表评论  【EndNote】   【RefMan】   【BibTex】
←前一篇|后一篇→ 过刊浏览    高级检索
本文已被:浏览 4066次   下载 2201  
风电功率爬坡事件作用下考虑时序特性的系统风险评估
何成明1, 王洪涛1, 王春义2, 韦仲康3
1.山东大学 电网智能化调度与控制教育部重点实验室,山东 济南 250061;2.国网山东省电力有限公司,山东 济南 250001;3.国网冀北电力有限公司,北京 100053
摘要:
与常规的风电功率随机波动相比,风电功率爬坡事件具有明显的时序特性。为准确评估其对系统运行风险的影响,分析风电功率爬坡事件的特点及发生过程,并基于非序贯蒙特卡罗模拟法推导与之相适应的常规机组停运模型。通过对常规机组可能停运时刻和对应的运行状态分别进行抽样,考虑爬坡事件与常规机组停运之间的时序关系对评估结果的影响。在计及低频减载及AGC调节作用的基础上,采用频率越限次数和失负荷期望对系统运行风险进行评估。以IEEE RTS 24节点系统为例,对多种场景下系统运行风险进行评估及对比分析,验证了所提模型的有效性。
关键词:  风电  爬坡事件  风险评估  时序特性  蒙特卡罗法
DOI:
分类号:
基金项目:国家高技术研究发展计划(863计划)资助项目(2011-AA05A101);国家自然科学基金资助项目(51177092)
Risk assessment considering time-sequence characteristics for power system with wind power ramp event
HE Chengming1, WANG Hongtao1, WANG Chunyi2, WEI Zhongkang3
1.Key Laboratory of Power System Intelligent Dispatch and Control of Ministry of Education,Shandong University,Ji’nan 250061,China;2.State Grid Shandong Electric Power Company,Ji’nan 250001,China;3.State Grid Jibei Electric Power Company,Beijing 100053,China
Abstract:
Different from the normal wind power stochastic volatility,the wind power ramp event has obvious time-sequence characteristics. In order to accurately assess its impact on the risk of system operation,its characteristics and development process are analyzed and a corresponding outage model is deduced based on the non-sequential Monte Carlo simulation method for the conventional generator. The possible outage time and corresponding operating state of conventional generator are sampled respectively and the impact of time-sequence relationship between the ramp event and the outage of conventional generator on the result of assessment is considered. With the consideration of under-frequency load-shedding and AGC regulation,the frequency violation degree and load-loss expectation are adopted to assess the risk of system operation. The risk of system operation is assessed and analyzed in multiple scenarios for IEEE RTS 24-bus system,verifying the effectiveness of the proposed model.
Key words:  wind power  ramp event  risk assessment  time-sequence characteristics  Monte Carlo methods