引用本文:陈 亮,顾雪平,贾京华.考虑后续恢复影响的扩展黑启动方案多目标优化与决策[J].电力自动化设备,2014,34(2):
CHEN Liang,GU Xueping,JIA Jinghua.Multi-objective optimization and decision making of extended black-start scheme considering subsequent restoration influence[J].Electric Power Automation Equipment,2014,34(2):
【打印本页】   【HTML】   【下载PDF全文】   查看/发表评论  【EndNote】   【RefMan】   【BibTex】
←前一篇|后一篇→ 过刊浏览    高级检索
本文已被:浏览 4882次   下载 1964  
考虑后续恢复影响的扩展黑启动方案多目标优化与决策
陈 亮1, 顾雪平1, 贾京华2
1.华北电力大学 电气与电子工程学院,河北 保定 071003;2.河北电力调度通信中心,河北 石家庄 050021
摘要:
综合考虑恢复初期阶段和后续阶段,提出一种扩展黑启动方案的多目标优化方法。以初期阶段内加权发电量最大化、尽快搭建系统的骨架网络和选择运行性能尽可能利于后续系统电压调整的被启动机组为优化目标,综合考虑机组启动约束和系统运行约束,建立扩展黑启动方案的多目标优化模型,然后结合快速非支配排序遗传算法(NSGA-Ⅱ)与Dijkstra法对扩展黑启动方案求解出Pareto最优解集。最后综合决策者的偏好因素和决策矩阵的客观信息,进行基于模糊熵权的Vague集多属性决策分析,选取出最满意的扩展黑启动优化方案。以新英格兰10机39节点系统为算例验证了所提方法的有效性。
关键词:  电力系统  黑启动  系统恢复  优化  约束  决策  Vague集  模糊熵  模型
DOI:
分类号:
基金项目:高等学校博士学科点专项科研基金资助项目(2011003 -6110007);河北省自然科学基金资助项目(E2011502025)
Multi-objective optimization and decision making of extended black-start scheme considering subsequent restoration influence
CHEN Liang1, GU Xueping1, JIA Jinghua2
1.School of Electrical and Electronic Engineering,North China Electric Power University,Baoding 071003,China;2.Hebei Power Dispatch and Communication Center,Shijiazhuang 050021,China
Abstract:
With the comprehensive consideration of initial and subsequent restoration stages,a multi-objective optimization model is built for the extended black-start schemes,which,with the constraints of unit startup and system operation,has three optimization objectives:maximize the weighted power generation during the initial stage,establish the system frame as soon as possible and select the black-start units beneficial to the subsequent regulation of system voltage. NSGA-Ⅱ(Non-dominated Sorting Genetic Algorithm) and Dijkstra algorithm are applied to solve the model and obtain Pareto solutions,from which the best extended black-start scheme is selected by applying the Vague-set multi-attributes decision-making based on fuzzy entropy weight and combining the subjective preference of decision-maker with the objective information of decision matrix. The effectiveness of the proposed method is validated by the case study of New England 10-unit 39-bus power system.
Key words:  electric power systems  black-start  system restoration  optimization  constraint  decision making  Vague sets  fuzzy entropy  models

用微信扫一扫

用微信扫一扫